§ 143-215.29. Supervision by qualified engineers; reports and modification during work.
(a) Any project for which the Commission's approval is required under G.S. 143-215.26, 143-215.27, and 143-215.28, and any project undertaken pursuant to an order of the Commission issued pursuant to this section or G.S. 143-215.32 or funded from the Fund established in G.S. 143-215.32A shall be designed and supervised by an engineer legally qualified in the State of North Carolina.
(b) During the construction, enlargement, repair, alteration or removal of a dam, the Commission may require such progress reports from the supervising engineer as it deems necessary.
(c) If during construction, reconstruction, repair, alteration or enlargement of any dam, the Commission finds the work is not being done in accordance with the provisions of the approval and the approved plans and specifications, it shall give written notice by registered mail or personal service to the person who received the approval and to the person in charge of construction at the dam. The notice shall state the particulars in which compliance has not been made, and shall order immediate compliance with the terms of the approval, and the approved plans and specifications. The Commission may order that no further construction work be undertaken until such compliance has been effected and approved by the Commission. A failure to comply with the approval and the approved plans and specifications shall render the approval revocable unless compliance is made after notice as provided in this section. (1967, c. 1068, s. 7; 1973, c. 1262, s. 23; 1977, c. 878, s. 5; 1987, c. 827, s. 154; 2021-180, s. 12.10(b).)